The physical and technical foundation of the Holistic Health and Fitness (H2F) System relies heavily on the deliberate fielding of specialized equipment and infrastructure. At the core of this effort are the Garrison Equipment Set (GES) and the specialized Information Technology (IT) package.

The GES is a comprehensive, multidisciplinary suite designed to establish fully functional garrison H2F operations, providing the essential tools required for athlete evaluation, rehabilitative treatment, and Soldier reconditioning. Complementing this physical kit, the IT package delivers dedicated computer workstations, peripherals, and networked printing systems to support the administrative, tracking, and communication needs of the H2F Performance Team (HPT). Together, these packages establish the robust physical and digital infrastructure necessary to empower embedded H2F Performance Team.

Overcoming Delays and Launching Deliveries

Following a series of logistical delays, the H2F GES and IT packages are officially moving into their active delivery phases. CPE-Ground is actively coordinating with impacted Brigades to ensure seamless shipping, delivery logistics, and strict hand-off accountability.

To maintain transparency and assist unit leadership in preparation, the projected delivery schedule for FY25 resourced HPTs is detailed below.

PROJECTED DELIVERY DATE LOCATION PACKAGE TYPE

| 21-27 July | Hawaii | IT Package

28 July Fort Bragg, NC IT Package

29 July Fort Belvoir, VA IT Package

4-5 August South Korea IT Package

4 August Germany IT Package

5 August Italy IT Package

2 September Fort Stewart, GA IT Package

9-10 September Fort Hood, TX GES & IT Packages

16 September Fort Sill, OK GES & IT Packages

16 September Fort Carson, CO GES & IT Packages

23 September Fort Leonard Wood, MO GES & IT Packages

23 September Fort Riley, KS GES & IT Packages

29 September Fort Irwin, CA GES & IT Packages

Looking Ahead: FY26 Deliveries

Upon successful distribution to all FY25 resourced units, CPE-Ground will transition immediately to coordinating and executing deliveries for FY26 resourced units. Procurement funds have been successfully awarded, and the primary vendor is currently building and securing the required equipment sets. Anticipated deliveries for FY26 units are projected to begin in January 2027.

Col. Lesher serves as the Physical Domain Lead with the H2F Directorate.