Fort McCoy’s Directorate of Public Works (DPW) and Xcel Energy continue to work together to finish the process of changing the electrical grid on post from a Delta Electrical System to a Wye Electrical System, Fort McCoy DPW officials said.
Work on this switchover has been ongoing since 2022, officials said, and during November and December 2025, workers continued to work on the project.
Wye is a three-phase electrical system that uses a wire for each electrical leg and a separate neutral wire.
Delta is also a three-phase but uses one of the legs as the neutral, so it only has three wires. Work will continue throughout the year.
At the website, https://electricityforum.com, a comparison between Wye and Delta was made. It discussed some of the benefits of the Wye system.
“Wye connections, with their neutral point, are common in low-voltage distribution systems, allowing for single-phase loads to be connected alongside three-phase loads,” the website states. “Wye connections provide the flexibility of both line-to-line and line-to-neutral voltages.”
Brandon Gronau, engineering technician with the Fort McCoy Directorate of Public Works Energy Branch, discussed the ongoing work in a previous news article.
“We — Fort McCoy and Xcel — are in the process of changing from a Delta Electrical System to a Wye Electrical System,” Gronau said. “The basics of that is just how the system is wired. Wye is a three-phase electrical system that uses a wire for each electrical leg and a separate neutral wire. Delta is also a three-phase but uses one of the legs as the neutral, so it only has three wires.”
Gronau said Xcel wanted to do this because they are the installation’s electrical privatization contractor, and they own all of the electrical infrastructure on post. Work has been steady for nearly since it started.
“Delta can be an unreliable system and is outdated,” Gronau said. “We were the only Delta system that Xcel has in the state, so in order to standardize all of their equipment they made the decision to change us over, too.”
Gronau said the switch is about resiliency in the system at Fort McCoy.
“Because Xcel is changing everything anyway, we decided that we wanted to move all of our overhead electrical that is inside the cantonment area underground as part of our move to making Fort McCoy more energy resilient,” Gronau said at the start of the switchover. “So, it just makes sense to do it all at the same time. We opted to only do the cantonment area, so they were replacing the poles on South Post to upgrade the infrastructure to support the change.”
According to the Office of the Assistant Secretary of the Army for Installations, Energy and Management at https://www.asaie.army.mil/Energy_and_Sustainability, projects like this are important for not just Fort McCoy’s future but the Army as well.
“Secure and reliable access to energy and water is essential to ensuring that the Total Army is ready to deploy, fight, and win across the entire spectrum of conflict,” the website states. “The Army’s Energy and Sustainability programs, to include installation and operational energy, support the Army’s priorities of readiness, modernization, reform, and alliances and partnerships.
“Army installations, where our Soldiers live, train, and deploy from, must have assured access to energy and water to enhance mission readiness,” the website states. “In order to be prepared to conduct operations both today and in the future, the Army is integrating energy and water considerations across the enterprise by focusing on resilience, efficiency, and affordability.”
Fort McCoy’s motto is to be the “Total Force Training Center.”
Located in the heart of the upper Midwest, Fort McCoy is the only U.S. Army installation in Wisconsin.
The installation has provided support and facilities for the field and classroom training of more than 100,000 military personnel from all services nearly every year since 1984.
Learn more about Fort McCoy online at https://home.army.mil/mccoy, on Facebook by searching “ftmccoy,” on Flickr at https://www.flickr.com/photos/fortmccoywi, and on X (formerly Twitter) by searching “usagmccoy.”
Also try downloading the My Army Post app to your smartphone and set “Fort McCoy” or another installation as your preferred base. Fort McCoy is also part of Army’s Installation Management Command where “We Are The Army’s Home.”
1 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL2 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL3 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL4 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL5 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL6 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL7 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL8 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL9 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL10 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL11 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL12 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL13 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL14 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL15 / 15Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
1 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL2 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL3 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL4 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL5 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL6 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL7 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL8 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL9 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL10 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL11 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL12 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL13 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL14 / 14Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
1 / 13Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL2 / 13Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL3 / 13Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL4 / 13Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL5 / 13Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL6 / 13Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL7 / 13Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL8 / 13Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL9 / 13Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL10 / 13Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL11 / 13Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL12 / 13Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL13 / 13Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
1 / 12Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL2 / 12Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL3 / 12Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL4 / 12Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL5 / 12Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL6 / 12Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL7 / 12Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL8 / 12Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL9 / 12Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL10 / 12Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL11 / 12Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL12 / 12Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
1 / 11Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL2 / 11Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL3 / 11Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL4 / 11Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL5 / 11Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL6 / 11Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL7 / 11Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL8 / 11Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL9 / 11Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL10 / 11Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL11 / 11Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
1 / 10Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL2 / 10Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL3 / 10Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL4 / 10Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL5 / 10Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL6 / 10Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL7 / 10Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL8 / 10Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL9 / 10Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL10 / 10Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
1 / 9Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL2 / 9Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL3 / 9Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL4 / 9Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL5 / 9Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL6 / 9Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL7 / 9Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL8 / 9Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL9 / 9Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
1 / 8Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL2 / 8Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL3 / 8Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL4 / 8Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL5 / 8Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL6 / 8Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL7 / 8Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL8 / 8Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
1 / 7Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL2 / 7Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL3 / 7Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL4 / 7Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL5 / 7Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL6 / 7Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL7 / 7Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
1 / 6Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL2 / 6Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL3 / 6Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL4 / 6Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL5 / 6Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL6 / 6Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
1 / 5Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL2 / 5Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL3 / 5Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL4 / 5Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL5 / 5Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
1 / 4Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL2 / 4Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL3 / 4Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL4 / 4Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
1 / 3Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL2 / 3Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL3 / 3Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
1 / 2Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)VIEW ORIGINAL2 / 2Show Caption +Hide Caption –
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
Contractors work on power lines Dec. 11, 2025, on the cantonment area at Fort McCoy, Wis. The work is part of an ongoing electrical grid upgrade at the installation where the post will go from a from a Delta Electrical System to a Wye Electrical System. Fort McCoy Directorate of Public Works officials are working the switch with energy provider Xcel Energy. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: U.S. Army)VIEW ORIGINAL
Social Sharing