1 / 13Show Caption +Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project, known as the Fort McCoy East Barracks Project, is shown on Nov. 15, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL2 / 13Show Caption +Hide Caption –
The construction area for a new $28.08 million barracks building is shown Nov. 15, 2024, at Fort McCoy, Wis., as progress on the facility continues. The contractor for the project, BlindermanPower (Construction), received the notice to proceed with construction on Sept. 26, 2023, and has 780 calendar days to complete the project. The project requires building a four-story, 60,000-square-foot barracks about to house 400 people. Two other barracks of the same specifications have already been built in the same block at the installation since 2019. Overall, it is part of a big transformation taking place at the 1600 block that includes the building of four barracks — two of which are already done, three brigade headquarters buildings, and two planned transient training officer quarters, according to the Fort McCoy Directorate of Public Works. This project is managed by the Army Corps of Engineers and as of mid-September 2024 the project was 45 percent complete. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL3 / 13Show Caption +Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project, known as the Fort McCoy East Barracks Project, is shown on Nov. 15, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL4 / 13Show Caption +Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project, known as the Fort McCoy East Barracks Project, is shown on Nov. 15, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL5 / 13Show Caption +Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project, known as the Fort McCoy East Barracks Project, is shown on Nov. 15, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL6 / 13Show Caption +Hide Caption –
The construction area for a new $28.08 million barracks building is shown Nov. 15, 2024, at Fort McCoy, Wis., as progress on the facility continues. The contractor for the project, BlindermanPower (Construction), received the notice to proceed with construction on Sept. 26, 2023, and has 780 calendar days to complete the project. The project requires building a four-story, 60,000-square-foot barracks about to house 400 people. Two other barracks of the same specifications have already been built in the same block at the installation since 2019. Overall, it is part of a big transformation taking place at the 1600 block that includes the building of four barracks — two of which are already done, three brigade headquarters buildings, and two planned transient training officer quarters, according to the Fort McCoy Directorate of Public Works. This project is managed by the Army Corps of Engineers and as of mid-September 2024 the project was 45 percent complete. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL7 / 13Show Caption +Hide Caption –
The construction area for a new $28.08 million barracks building is shown Nov. 15, 2024, at Fort McCoy, Wis., as progress on the facility continues. The contractor for the project, BlindermanPower (Construction), received the notice to proceed with construction on Sept. 26, 2023, and has 780 calendar days to complete the project. The project requires building a four-story, 60,000-square-foot barracks about to house 400 people. Two other barracks of the same specifications have already been built in the same block at the installation since 2019. Overall, it is part of a big transformation taking place at the 1600 block that includes the building of four barracks — two of which are already done, three brigade headquarters buildings, and two planned transient training officer quarters, according to the Fort McCoy Directorate of Public Works. This project is managed by the Army Corps of Engineers and as of mid-September 2024 the project was 45 percent complete. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL8 / 13Show Caption +Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project, known as the Fort McCoy East Barracks Project, is shown on Nov. 15, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL9 / 13Show Caption +Hide Caption –
The construction area for a new $28.08 million barracks building is shown Nov. 15, 2024, at Fort McCoy, Wis., as progress on the facility continues. The contractor for the project, BlindermanPower (Construction), received the notice to proceed with construction on Sept. 26, 2023, and has 780 calendar days to complete the project. The project requires building a four-story, 60,000-square-foot barracks about to house 400 people. Two other barracks of the same specifications have already been built in the same block at the installation since 2019. Overall, it is part of a big transformation taking place at the 1600 block that includes the building of four barracks — two of which are already done, three brigade headquarters buildings, and two planned transient training officer quarters, according to the Fort McCoy Directorate of Public Works. This project is managed by the Army Corps of Engineers and as of mid-September 2024 the project was 45 percent complete. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL10 / 13Show Caption +Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project, known as the Fort McCoy East Barracks Project, is shown on Nov. 15, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL11 / 13Show Caption +Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project, known as the Fort McCoy East Barracks Project, is shown on Nov. 15, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL12 / 13Show Caption +Hide Caption –
The construction area for a new $28.08 million barracks building is shown Nov. 15, 2024, at Fort McCoy, Wis., as progress on the facility continues. The contractor for the project, BlindermanPower (Construction), received the notice to proceed with construction on Sept. 26, 2023, and has 780 calendar days to complete the project. The project requires building a four-story, 60,000-square-foot barracks about to house 400 people. Two other barracks of the same specifications have already been built in the same block at the installation since 2019. Overall, it is part of a big transformation taking place at the 1600 block that includes the building of four barracks — two of which are already done, three brigade headquarters buildings, and two planned transient training officer quarters, according to the Fort McCoy Directorate of Public Works. This project is managed by the Army Corps of Engineers and as of mid-September 2024 the project was 45 percent complete. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL13 / 13Show Caption +Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project, known as the Fort McCoy East Barracks Project, is shown on Nov. 15, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL
Contractors work on a new $27.3 million transient training troops barracks project, known as the Fort McCoy East Barracks Project, is shown on Nov. 15, 2024, at Fort McCoy, Wis.
Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million.
L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post.
They also recently built the new brigade headquarters building located in the same block as the barracks buildings.
The exact contract amount for the project was $27,287,735.
In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.”
The building will be able to house up to 400 people and will be more than 60,000 square feet.
This project is managed by the U.S. Army Corps of Engineers.
Fort McCoy’s motto is to be the “Total Force Training Center.” Located in the heart of the upper Midwest, Fort McCoy is the only U.S. Army installation in Wisconsin.
The installation has provided support and facilities for the field and classroom training of more than 100,000 military personnel from all services nearly every year since 1984.
Learn more about Fort McCoy online at https://home.army.mil/mccoy, on Facebook by searching “ftmccoy,” on Flickr at https://www.flickr.com/photos/fortmccoywi, on X (formerly Twitter) by searching “usagmccoy,” on Instagram at https://www.instagram.com/fortmccoywi, and on YouTube at https://www.youtube.com/@fortmccoy.