1 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 25, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
2 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 25, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
3 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 25, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
4 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 25, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
5 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 25, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
6 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 25, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
7 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 24, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
8 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 19, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
9 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 19, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
10 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 18, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
11 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 12, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
12 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 12, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
13 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 12, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
14 / 14
Show Caption +
Hide Caption –
Contractors work on a new $27.3 million transient training troops barracks project July 12, 2024, at Fort McCoy, Wis. Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million. L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735. In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people and will be more than 60,000 square feet. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: Scott Sturkol)
VIEW ORIGINAL
Less than three months after the groundbreaking of the fiscal year 2023 Transient Training Troops Barracks Project, also called the Fort McCoy East Barracks Project, and contractor L.S. Black Constructors has the base of the building started as August begins.
Since May 13, construction the fourth, $27.3 million barracks project have been in high gear by the contractor who was awarded the project in February. The exact contract amount for the project when it was awarded was $27,287,735.
L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings.
In a July 26 update about the project, Nathan Butts with the Resident Office of the Army Corps of Engineers at Fort McCoy said the contractor has made significant progress.
“Forms and rebar continue to be placed for the footings,” Butts wrote in the update. “Utility services continue to be placed. … Concrete placement for the footings continues. … Safety audit with the contractor was completed.”
Throughout May and well into June a lot of work went into preparing the site for construction. Then going into July actual construction started and now footings are in place as August begins. The contract duration is scheduled for completion in 780 calendar days, Army Corps of Engineer contract documents show.
In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.” The building will be able to house up to 400 people.
According to the scope of work, it’s going to be made of permanent construction with reinforced concrete foundations; concrete floor slabs; structural steel frames; steel stud infill; masonry veneer walls; prefinished standing seam metal roofing; heating, ventilation, and air conditioning capabilities; plumbing; mechanical systems; and electrical systems. Supporting facilities include land clearing, concrete sidewalk paving, general site improvements, and utility connections.
“The building also is being built with the latest in construction materials and include state-of-the-art physical security and energy-saving measures,” the statement of work shows.
In the backdrop of this project is the ongoing third barracks project — a $28 million project that was awarded in June 2023 to BlindermanPower (Construction). That project is currently at 27 percent complete and continuing to be completed swiftly.
All of this work continues with the master plan for the 1600 block that will include not only the four barracks but also three 20,000-square-foot brigade headquarters buildings — one of which is done — and two 160-room officer quarters, said Master Planner Brian Harrie with the Fort McCoy Directorate of Public Works.
The Fort McCoy Executive Summary, available at https://www.dvidshub.net/publication/issues/71646, also shows the installation makes continuous improvements to provide a plethora of training capabilities for service members.
“Throughout the last decade, Fort McCoy experienced unprecedented facility modernization, training area development and expansion, increased training and customer support capability, and improved quality-of-life opportunities,” the summary states. “From unmanned aerial vehicles to urban training facilities, to live-fire ranges and virtual-training environments, Fort McCoy is prepared to meet the training needs of the Army in the 21st century.”
Also to be completed soon, Army Corps of Engineer officials said earlier in 2024, is the awarding of a contract for one of the officer quarters buildings. Harrie has stated in previous news articles this entire transformation of this block at McCoy is known as the 1600 Block Transient Training Campus Plan.
See more news about the U.S. Army Corps of Engineers by visiting https://www.usace.army.mil/Media/News.
Fort McCoy’s motto is to be the “Total Force Training Center.”
Located in the heart of the upper Midwest, Fort McCoy is the only U.S. Army installation in Wisconsin.
The installation has provided support and facilities for the field and classroom training of more than 100,000 military personnel from all services nearly every year since 1984.
Learn more about Fort McCoy online at https://home.army.mil/mccoy, on Facebook by searching “ftmccoy,” on Flickr at https://www.flickr.com/photos/fortmccoywi, and on X (formerly Twitter) by searching “usagmccoy.”
Also try downloading the My Army Post app to your smartphone and set “Fort McCoy” or another installation as your preferred base. Fort McCoy is also part of Army’s Installation Management Command where “We Are The Army’s Home.”