FORT SILL, Okla. (July 9, 2015) -- The Fort Sill Directorate of Public Works has a road repair contract that will occur in 10 locations. Road work will begin July 21. Roads will be milled and resurfaced with new asphalt. No range roads will be affected.
Three or more areas may be under construction at any given time. Traffic will be rerouted or flagged with one lane in each work area open to traffic at all times.
Please obey posted speed limits, flag persons and pilot vehicles. Be careful of work crews and construction vehicles. If possible, motorist are advised to find alternate routes during times of construction.
The first eight areas and their schedules are:
- Bateman Rd. on the south side of Bldg. 1655 to the east parking lot; July 21 through Sept. 2.
- The driveway east of Bldg. 3328 (NAF Warehouse) from Mow-Way Road to Wilson Road; Aug. 7 through Sept. 11.
- Bessinger Street from Berry to Gordon streets; Aug. 16 through Oct. 6.
- Crane Avenue from Minor north to Hunt Road; Aug. 16 through Oct. 10.
- Jones Road from Austin Road to Ringgold Road; Aug. 24 through Oct. 15.
- Austin Road from Currie Road to Fort Sill Boulevard; Sept. 11 through Nov. 9.
- Hamilton Road from Randolph Road to Geronimo Road. This includes a wide repair of the north end of the parking lot south of McNair Hall (Bldg. 455); Sept. 19 through Nov. 18.
- Bragg Road from Ringgold Road to Thomas Street, including the east and west legs of the "Y" at Thomas Street; Sept. 27 through Nov. 27.
The remaining two areas are of a greater scale and will resurface the entire length of Geronimo Road from Hamilton Road to Post Road, including the intersection of Geronimo and Sheridan roads. This project is scheduled to begin and be completed in 2016.
For more information, contact the DPW Construction Branch at 580-442-3898.