Army leaders convene to unify organic industrial base and secure ‘Arsenal of Freedom’

By Lt. Col. Orlandon Howard, U.S. Army Communications and Outreach OfficeOctober 28, 2026

Watervliet forging ahead with key modernization projects
Watervliet Arsenal forge workers monitor a cannon tube being processed through the current rotary forge. Watervliet Arsenal plans to replace the forge with a new, more capable forge in 2026. (U.S. Army photo) (Photo Credit: Matthew Day) View original

JOINT BASE MYER-HENDERSON HALL, Va. — The Army hosted the first Organic Industrial Base Workload Summit at Joint Base Myer-Henderson Hall, Oct. 20–22, 2026. It brought together senior leaders, acquisition executives, depot commanders, and congressional staff members to align industrial workload capacity, modernization plans, and immediate readiness requirements across the service.

“This is the first time we’ve brought the whole of Army together focused on our Arsenal of Freedom for the OIB,” said Jesse Tolleson, acting deputy undersecretary of the Army. “This effort centers on developing an Army Strategic Plan for our OIB that is resource-informed with program plans and modernization strategies in support of our joint force.”

Mr. Tolleson OIB Workload Summit
Mr. Jesse Tolleson, acting deputy undersecretary of the Army, addresses participants at Joint Base Myer-Henderson Hall during the first Organic Industrial Base (OIB) Workload Summit held Oct. 20–22, 2026. The three-day summit focused on aligning industrial workload capacity with immediate operational readiness requirements. (Photo Credit: Leroy Council) View original
Re-anchoring the Industrial Base

The Army’s OIB consists of 23 government-owned installations, including repair depots, manufacturing arsenals, and ammunition plants — that build, rebuild, repair and upgrade military equipment. For decades, planning for these facilities happened in isolation, often relying on separate forecasts, disconnected program timelines and year-to-year maintenance budgets.

As the Army prepares for great power competition and large-scale combat operations, industrial capacity directly affects the service's operational endurance and surge capability. To address this, the Army established the Workload Summit, an enterprise planning process that aligns its depots, arsenals and ammunition plants with future operational demand.

The summit marks a significant transition from decentralized forecasting toward a transparent, enterprise-wide ledger that directs resources to the systems soldiers rely on most.

Letterkenny Army Depot hosts AMCOM symposium focused on OIB modernization
1 / 2 220803-A-BS696-1194
CHAMBERSBURG, Pa.

David Pollock, director of the Directorate of Supply and Transportation at Letterkenny Army Depot, demonstrates the Hive data analytic tool to subject matter experts in various disciplines during the U.S. Army Aviation and Missile Command Organic Industrial Base Symposium Aug. 2-4 at Letterkenny Army Depot, Pennsylvania.

The symposium, hosted by Letterkenny Army Depot, was focused on aligning the strategic direction of the AMCOM OIB with the Army modernization strategy to ensure that the depots can sustain the multi-domain force of 2035.

The Automated Storage and Retrieval System Hive analytics tool launched Sept. 16, 2020, and provides users a visual depiction of centralized workload demands, allowing workers to evaluate discrepancies and level workload amongst all areas in real time.
(U.S. Army photo by Pam Goodhart) (Photo Credit: Pam Goodhart) View original
LEAD Avenger sustainment
2 / 2 231129-A-BS696-4579
CHAMBERSBURG, Pa.
April Bookwalter, an electronic mechanic assigned to the Close Combat Missile System work center at Letterkenny Army Depot, repairs a remote control unit of an Avenger fire unit Nov. 29, 2023.
(U.S. Army photo by Pam Goodhart) (Photo Credit: Pam Goodhart) View original
What Workload Means on the Factory Floor

In military operations, workload represents the tangible, funded volume of maintenance, overhaul, and manufacturing assigned to Army facilities. It translates dollars into the physical labor hours required to sustain combat formations from overhauling helicopter engines and remanufacturing combat vehicle tracks to forging cannon tubes and recertifying guided missile systems.

"Workload is not simply a planning number; it is the foundation for Army readiness," Tolleson said. "It determines whether we retain skilled artisans and technicians, preserve critical production lines, modernize facilities, and maintain equipment on time."

"Workload directly drives our ability to generate endurance and prevail in any large-scale combat operation, and the OIB stands at the center of that capability," Tolleson added.

To integrate acquisition, sustainment, and long-range programming, the Army established the Organic Industrial Base Integration Office (OIB-IO) as the single enterprise integrator. The summit served as the office's first major initiative, convening representatives from the Office of the Assistant Secretary of the Army for Acquisition, Logistics, and Technology (ASA(ALT)), Assistant Secretary of the Army for Financial Management & Comptroller (ASA(FM&C), Army Materiel Command (AMC), Headquarters Department of the Army staff sections (G-2, G-3, G-4, and G-8), and leadership from 13 Government-Owned, Government-Operated (GOGO) installations and munitions centers.

During the sessions, participants consolidated isolated forecasts into a synchronized baseline of total industrial maintenance requirements for inclusion in Program Objective Memorandum (POM) 29.

Designing Sustainment into Initial Acquisition

Hon. Brent Ingraham, Assistant Secretary of the Army for Acquisition, Logistics, and Technology, emphasized that weapon systems must be sustainable from the start. He reinforced the necessity of disciplined, data-informed planning across programs and the industrial base.

"Delivering a new system to the field is only the beginning of the acquisition story," Ingraham said. "A capability that cannot be sustained when it meets combat is not an asset; it is an operational liability."

Ingraham directed Program Acquisition Executives and Program Managers to integrate depot requirements into initial acquisition strategies. He noted that programs must budget for long-term maintenance plans, specialized tooling, and technical data rights from inception rather than address them after fielding.

LEAD Blue Light Scanning
1 / 2 220314-A-BS696-1218
CHAMBERSBURG, Pa.
Kennon Matthews, lead metrologist, Letterkenny Army Depot, performs blue light scanning on a High Mobility Artillery Rocket System cab March 14, 2022.
Blue-light scanning technology was initially acquired to generate surface measurement analyses of turrets for the Extended Range Cannon Artillery program at Letterkenny. Still, artisans and engineers have expanded the technology into other programs, increasing Letterkenny’s adaptability to production program needs through faster turn-around times for reverse engineering.

(U.S. Army photo by Pam Goodhart) (Photo Credit: Pam Goodhart) View original
LEAD Hellfire missile program
2 / 2 230103-A-JT832-1014
CHAMBERSBURG, Pa.
Todd Santiago, an electronics technician within the Directorate of Missile and Aerospace Readiness at Letterkenny Army Depot, utilizes an inert training missile to familiarize himself with the disassembly, assembly and component replacement procedures for the Hellfire missile program Jan. 3.

The training missiles provide an opportunity for technicians to start learning the structure of the missiles and processes used for maintenance.
(U.S. Army photo by Josh Shinn) (Photo Credit: Joshua Shinn) View original
Prioritizing Joint Fleet Readiness

Lt. Gen. Gavin Lawrence, deputy commanding general and acting commander of AMC, the command responsible for overseeing and executing the service’s industrial base plans, stressed that the summit must produce concrete readiness gains for operational units.

"The objective is not workload for its own sake," Lawrence said. "The objective is readiness. Readiness in terms of more available equipment, more responsive sustainment, and greater resilience in the force."

Lawrence outlined three primary priorities for the enterprise:

  • Improve Readiness Today: Identify opportunities where organic depot capacity can reduce repair cycle times, resolve component shortages, and return combat-ready equipment to units more rapidly.
  • Secure Future Enablers: Identify requirements early, including technical data rights, specialized tooling, modern facilitie, and artisan skills—to avoid sustainment constraints later.
  • Synchronize Multi-Year Workload: Establish predictable demand signals that enable depots to retain skilled machinists, welders, and technicians while aligning capacity with Army needs.
Evaluating Enterprise Portfolios

During the working sessions, technical experts and program managers evaluated operational capacity, supply constraints, and requirements across six critical portfolios:

  • Maneuver Ground: Focused on component repair lines, such as road wheels, wiring harnesses, and T161 track, while assessing heavy combat vehicle overhauls for Abrams tanks, Bradley Fighting Vehicles, Strykers, and M88 recovery vehicles.
  • Maneuver Air: Evaluated aircraft overhaul rates for UH-60 Black Hawks, AH-64 Apaches, and CH-47 Chinooks, addressing repair strategies for crash and battle damage as well as component pipeline stabilization.
  • Fires: Assessed their portfolio’s resource requirements encompassing air and missile defense systems (PATRIOT, IBCS, LTAMDS, THAAD) and long-range precision fires (HIMARS, MLRS, PrSM).
  • Agile Sustainment & Ammunition: Evaluated energetics capabilities, coordination with the Defense Logistics Agency for organic parts sourcing, and sustainment for tactical wheeled vehicles (FMTV, HEMTT).
  • Command, Control, and Communications (C2/Counter-C2): Addressed the sustainment of radars, communication suites, and mobile command nodes, alongside integration schedules for systems like the Tactical Intelligence Targeting Access Node (TITAN).
  • Layered Protection & Integration: Reviewed chemical defense capabilities production at direct labor-hour cost structures, and options to separate base operating costs from depot labor rates to maintain competitive pricing.

The Path Forward

By the summit's close, the OIB-IO team consolidated the working group proposals into an enterprise-level workload plan headed for Army senior leader review. The resulting roadmap links program budgets, modernization goals, and depot operations into a unified strategic plan designed to keep equipment ready and resilient across the joint force.

The synchronized baseline provides the analytical foundation necessary to align equipment procurement, resourcing decisions, and depot maintenance into upcoming defense budgets.

"We must balance readiness, modernization, affordability, technical feasibility, capacity, workforce, supply chain resilience and the Army’s ability to surge, when called upon by our nation," Ingraham said. "What this summit does is establish the disciplined, data-informed process that allows us to make those decisions deliberately and transparently."