Division commander’s visit highlights people, partnerships in mission delivery

By Noe GonzalezFebruary 24, 2026

Engineer briefs LRD commander at Chickamauga Lock Replacement Project
1 / 2 Show Caption + Hide Caption – CHATTANOOGA, Tenn. (Feb. 20, 2026) – Ryan Cleary (right), a civil engineer for the U.S. Army Corps of Engineers Nashville District, briefs Col. Herlihy (second from left), commander of the Great Lakes and Ohio River Division, on the installation and welding progress of the miter gates at the Chickamauga Lock Replacement Project in Chattanooga, Tennessee, Feb. 20, 2026. Looking on are Lt. Col. Guillermo Guandique (left), Nashville District commander, and Bob Winters (second from right), a project manager for the lock. (Photo Credit: Noe Gonzalez) VIEW ORIGINAL
A look inside Chickamauga's new lock chamber
2 / 2 Show Caption + Hide Caption – CHATTANOOGA, Tenn. (Feb. 20, 2026) – Massive miter gates are stacked inside the new 110-by-600-foot lock chamber at the U.S. Army Corps of Engineers Nashville District's Chickamauga Lock Replacement Project in Chattanooga, Tennessee, Feb. 20, 2026. Crews are currently in the process of installing and welding the 14 new gates, a critical phase in the construction that will ultimately lead to an 80% increase in navigation efficiency on the Tennessee River. (Photo Credit: Noe Gonzalez) VIEW ORIGINAL

NASHVILLE, Tenn.(Feb. 24, 2026) – To truly understand the challenges of modernizing America’s inland waterways, you have to walk the ground and talk to the people who make it happen every day. That’s exactly what Col. Daniel J. Herlihy, commander of the Great Lakes and Ohio River Division, did during a visit last week to two of the Nashville District's most complex and critical projects.

The colonel, who assumed command of the division Aug. 13, 2025, oversees seven districts across 17 states. He visited the Nashville District Feb.18-20 to get a firsthand look at major infrastructure projects and meet the teams making them happen. His tour focused on people and operations, with stops at Center Hill Dam in Lancaster, Tennessee, and Chickamauga Lock in Chattanooga, Tennessee.

Nashville District Chief Briefs LRD Commander on Center Hill Project
LANCASTER, Tenn. (Feb. 19, 2026) – Anthony Rodino (right), chief of the Programs and Project Delivery Branch for the U.S. Army Corps of Engineers Nashville District, briefs Col. Herlihy (left), commander of the Great Lakes and Ohio River Division, during a tour of Center Hill Dam in Lancaster, Tennessee, Feb. 19, 2026. Rodino provided an overview of the dam's operations and the status of the spillway gate replacement project. The U.S. Army Corps of Engineers Nashville District is replacing spillway gates at Wolf Creek Dam in Jamestown, Kentucky, and Center Hill Dam in Lancaster, Tennessee, to upgrade its flood risk and water management infrastructure in the Cumberland River Basin. In this photo, spillway gates are assembled on a barge at Center Hill Dam Feb. 19, 2026. (USACE Photo by Noe Gonzalez) (Photo Credit: Noe Gonzalez) VIEW ORIGINAL
“You can’t understand it until you walk on the ground and talk to the people and really get a firsthand view of the challenges and opportunity we have,” Herlihy said. “So, this is absolutely critical, it is something that I enjoy just getting that opportunity to see our folks.”
USACE team shows Herlihy spillway gates from inside Center Hill Dam
LANCASTER, Tenn. (Feb. 19, 2026) – U.S. Army Corps of Engineers subject matter experts and leaders, along with a contractor from American Bridge Company, show Col. Herlihy, commander of the Great Lakes and Ohio River Division, a close-up view of the spillway gates from inside the Pier 1 access hatch at Center Hill Dam in Lancaster, Tennessee, Feb. 19, 2026. The tour provided Herlihy with a detailed, firsthand perspective on the ongoing spillway gate replacement project. The U.S. Army Corps of Engineers Nashville District is replacing spillway gates at Wolf Creek Dam in Jamestown, Kentucky, and Center Hill Dam in Lancaster, Tennessee, to upgrade its flood (Photo Credit: Noe Gonzalez) VIEW ORIGINAL

Herlihy toured Center Hill Dam on the Caney Fork River Feb. 19, where a significant spillway gate replacement project is underway. Onsite, project leaders briefed him on the history that necessitated the replacement of the dam's eight massive spillway gates. Officials explained that during the wettest season on record in 2019, the lake rose to nearly 80% of its flood control capacity, placing immense pressure on the original 1948 gates. The gates, which have exceeded their design life, urgently needed replacement.

Greg Bishop, Nashville District project manager, summarized the mission for Herlihy.

American Bridge manager briefs LRD commander on gate project
LANCASTER, Tenn. (Feb. 19, 2026) – Josh Munzek (left), project manager for American Bridge Company, briefs Col. Herlihy, commander of the Great Lakes and Ohio River Division, on the status of the spillway gate replacement project at Center Hill Dam Feb. 19, 2026. The discussion took place on a barge where new gates were being assembled and welded for future installation. (Photo Credit: Noe Gonzalez) VIEW ORIGINAL
“Some of the structural members of some of the gates had deformed perhaps due to age. The project will replace all eight spillway gates so that we can ensure the safety of the public downstream for years to come,” Bishop said.

The new, heavier gates require modernizing the original lifting equipment. Project leaders detailed to Herlihy how the unique collaborative dynamic with contractor American Bridge Company has been crucial. By also holding the contract for a similar project at Wolf Creek Dam in Jamestown, Kentucky, lessons learned are transferred in real-time, enhancing efficiency and safety. This collaboration is reinforced by a good communication structure, including monthly leadership meetings and weekly progress meetings.

American Bridge Company contractors weld new Center Hill Dam gate
LANCASTER, Tenn. (Feb. 19, 2026) – Contractors from American Bridge Company weld a new spillway gate on a barge at Center Hill Dam in Lancaster, Tennessee, Feb. 19, 2026. The gate is being prepared for installation in June 2026 as part of a U.S. Army Corps of Engineers Nashville District project to replace aging gates at both Center Hill and Wolf Creek dams, upgrading flood risk management infrastructure in the Cumberland River Basin. (USACE Photo by Noe Gonzalez) (Photo Credit: Noe Gonzalez) VIEW ORIGINAL

Speaking with Herlihy about the partnership, Josh Munzek, project manager for American Bridge Company, said,

“We are ahead of schedule and constant communication is great. It’s been really relieving to have that communication, knowing that everybody’s looking towards one goal of completing the project safely and on time.”

Herlihy’s tour concluded Feb. 20 at the Chickamauga Lock Replacement Project in Chattanooga. There, he received an in-depth tour of the operations being used to address the "concrete growth" an alkali-aggregate reaction, that threatens the original 1940s-era lock. The new 110-by-600-foot lock is a mega-project that will dramatically improve efficiency on the Tennessee River, reducing commercial transit times by an estimated 80% and increasing capacity nine-fold.

During the visit, Tom Hale, operations manager for the Tennessee River, highlighted the strong, historic partnership between USACE and the Tennessee Valley Authority.

Chickamauga Lock Replacement Project makes progress
CHATTANOOGA, Tenn. (Feb. 20, 2026) – Construction progresses on the new lock chamber for the U.S. Army Corps of Engineers Nashville District's Chickamauga Lock Replacement Project in Chattanooga, Tennessee, shown Feb. 20, 2026. The chamber is 76 percent complete as part of a multi-contract effort to modernize the waterway. The new 110-by-600-foot lock will allow nine jumbo barges to pass through at once, a significant increase from the current single-barge capacity. (Photo Credit: Noe Gonzalez) VIEW ORIGINAL
“From 1925 until 1933 the USACE Nashville District operated Wilson Dam and Lock on the Tennessee River in Florence, Alabama. In 1933, President Franklin D. Roosevelt established TVA, but the Corps of Engineers maintained responsibility for the navigation mission,” Hale explained. “TVA is the owner of the locks, but USACE is a very proud partner… a very strong and effective relationship.”

Hale further detailed the immense economic impact of the waterway for Herlihy, noting the 10 navigation locks on the river provide more than 500 miles of navigation.

“On an annual basis, over 40 million tons of commodities will pass through these locks,” Hale said. “It is not just about moving products through the river. It is about empowering the economies and improving lives up and down this Tennessee River.”
Project manager briefs LRD commander on Chickamauga Lock
CHATTANOOGA, Tenn. (Feb. 20, 2026) – Cayce Grall, project manager for the U.S. Army Corps of Engineers Nashville District, briefs Col. Herlihy, commander of the Great Lakes and Ohio River Division, during a tour of the Chickamauga Lock Replacement Project in Chattanooga, Tennessee, Feb. 20, 2026. Progress on the multi-contract project includes the new lock chamber at 76 percent completion and the upstream approach wall at 70 percent, with the final contract awarded in February. The new 110-by-600-foot lock will process nine jumbo barges in one lockage, compared to one in the existing lock, an 80% increase in efficiency for the navigation industry. (Photo Credit: Noe Gonzalez) VIEW ORIGINAL

Throughout his visit, Herlihy emphasized that the strength of the Corps lies in its people. His sentiment was echoed by Nashville District leadership.

Lt. Col. Guillermo Guandique, Nashville District commander, said,

“The ability to get our senior leaders down to talk with our subject matter experts gives us confidence in their abilities and capabilities that we have the right people.”
Nashville District commander briefs LRD commander on Chickamauga Lock
CHATTANOOGA, Tenn. (Feb. 20, 2026) – Lt. Col. Guillermo Guandique, commander of the U.S. Army Corps of Engineers Nashville District, briefs Col. Herlihy, commander of the Great Lakes and Ohio River Division, during a tour of the Chickamauga Lock Replacement Project in Chattanooga, Tennessee, Feb. 20, 2026. Progress on the multi-contract project includes the new lock chamber at 76 percent completion and the upstream approach wall at 70 percent, with the final contract awarded in February. The new 110-by-600-foot lock will process nine jumbo barges in one lockage, compared to one in the existing lock, an 80% increase in efficiency for the navigation industry. (Photo Credit: Noe Gonzalez) VIEW ORIGINAL

The opportunity to see these projects up close and speak with the project managers, engineers and contractors is crucial in Herlihy’s understanding of the complexities and challenges.

Col. Herlihy meets with Nashville District team at Center Hill
LANCASTER, Tenn. (Feb. 19, 2026) – Col. Herlihy, commander of the Great Lakes and Ohio River Division, poses for a group photo with U.S. Army Corps of Engineers Nashville District leaders, project managers, engineers, and specialists in front of newly assembled spillway gates at Center Hill Dam in Lancaster, Tennessee, Feb. 19, 2026. The team briefed the commander on the progress of the major gate replacement project during his tour of the facility. (Photo Credit: Noe Gonzalez) VIEW ORIGINAL
“The key takeaways are the quality of the people that we have on the Nashville team working to getting the engineering right and deliver solutions for our nation,” he said.

The colonel recognized multiple team members throughout his visit, presenting them with division coins for their noteworthy contributions. These individuals, nominated by their supervisors, were honored for their commitment to excellence and teamwork.

LRD Commander Recognizes Nashville District Safety Specialist
LANCASTER, Tenn. (Feb. 19, 2026) – Col. Herlihy, commander of the Great Lakes and Ohio River Division (right), presents a division coin to David Darling, a safety specialist for the U.S. Army Corps of Engineers Nashville District, during a tour of the Center Hill Dam in Lancaster, Tennessee, Feb. 19, 2026. Darling was one of several team members nominated by supervisors and recognized by Herlihy during his visit for their outstanding contributions and commitment to excellence. (Photo Credit: Noe Gonzalez) VIEW ORIGINAL

As for his own priorities, Herlihy kept his message simple and direct.

“My priorities are to continue to deliver, and to take care of each other. If we do those two things, we’re winning.”

The public can obtain news, updates and information from the U.S. Army Corps of Engineers Nashville District on the district’s website at https://www.lrd.usace.army.mil/About/Districts/Nashville-District/, on Facebook at www.facebook.com/nashvillecorps and on X (formerly Twitter) at www.x.com/nashvillecorps. Follow us on LinkedIn for the latest Nashville District employment and contracting opportunities at https://www.linkedin.com/company/u-s-army-corps-of-engineers-nashville-district.