Late November and December 2025 have seen a fair amount of extreme cold weather, but the contractors for the $55.75 million Collective Training Officers Quarters Project at Fort McCoy kept building and moving forward.
On Nov. 21, the project was 33 percent complete, according to the U.S. Army Corps of Engineers. As of Dec. 19, that progress increased to 38 percent completed.
The project includes two buildings being constructed in a sizeable construction space of the installation’s 1600 block of the cantonment area. On the west building, the contractor has been busy finishing framing so they can then fully cover the building. On the east building, more of the exterior walls were receiving brick placement.
The contractor for the project, BlindermanPower (Construction), which has also completed another major project at Fort McCoy — the fiscal year-2022 funded South Barracks Project, was awarded a contract totaling $55,759,100, according to the Army Corps of Engineers. The notice to proceed was acknowledged on July 19, 2024. The contract duration is scheduled for completion in 1,260 calendar days.
In 2024, for numerous months, actual full construction of the new buildings had to wait for another contractor to move five World War II-era barracks buildings. Those are destined for a separate future project, Fort McCoy Directorate of Public Works (DPW) officials said.
The project description in the contract states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex.
“This facility is required to replace antiquated World War II-era wood transient training officer quarters currently being utilized to train Soldiers during major exercises, annual training, battle assembly, and mobilization at Fort McCoy,” the description states. “This facility will be designed with the ability to be winterized or deactivated during the winter months.”
Ken Green with the U.S. Army Corps of Engineers Resident Office at Fort McCoy said with the project now being 38 percent complete, the contractor hasn’t let weather slow them down.
In his Dec. 19 update, Green gave the latest actions.
“In the west building, exterior wall framing continued,” Green wrote in the update. “Mechanical, electrical, and plumbing rough-in continued. Interior and exterior spray foam continued. Interior rough-in framing and sheet rocking continued. Masonry continued on the west side section. Fluid applied air barrier completed. Standing seam roof panels staged.
“In the east building, structural steel erection continued for section B,” Green wrote. “Winterization continues. Exterior stud framing continued in section A and B. Interior stairs section A concrete placed. Exterior spray foam started on structural steel in-fills.”
The project description, also as stated in previous news articles, gives more information about how the project will continue to grow.
“When Fort McCoy is not stood up as a mobilization platform, its primary mission is to support the seasonal requirements of training … Army Reserve Soldiers,” the description states. “In order to conserve as much energy as possible, while also decreasing the funding necessary to field extended utility costs, this building will be deactivated when it is not being used for training.”
The contract requirements also show that work includes building a standing seam metal roof over rigid insulation on steel deck on structural trusses; using utility brick veneer over rigid insulation on steel studs with exterior glass mat gypsum sheathing; building a concrete floor on metal deck and on-grade; installing and elevator, aluminum doors and windows, gypsum board and metal frame partitions, steel door frames and steel doors, and acoustical ceilings; installing heating, ventilation, and air conditioning (HVAC) systems; completing plumbing, security, and electrical systems; and more.
The officer’s quarters project makes two active, large construction projects taking place in the 1600 block of the installation. All this work also continues with the master plan for the 1600 block that will include not only the four barracks but also three 20,000-square-foot brigade headquarters buildings — one of which is done — and now the two 160-room officer quarters, said Fort McCoy Directorate of Public Works officials.
Contract completion date is currently is Dec. 31, 2027.
See more news about the U.S. Army Corps of Engineers by visiting https://www.usace.army.mil/Media/News.
Fort McCoy’s motto is to be the “Total Force Training Center.”
Located in the heart of the upper Midwest, Fort McCoy is the only U.S. Army installation in Wisconsin.
The installation has provided support and facilities for the field and classroom training of more than 100,000 military personnel from all services nearly every year since 1984.
Learn more about Fort McCoy online at https://home.army.mil/mccoy, on Facebook by searching “ftmccoy,” on Flickr at https://www.flickr.com/photos/fortmccoywi, and on X (formerly Twitter) by searching “usagmccoy.”
Also try downloading the My Army Post app to your smartphone and set “Fort McCoy” or another installation as your preferred base. Fort McCoy is also part of Army’s Installation Management Command where “We Are The Army’s Home.”
1 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 20, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 20, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 20, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL15 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL16 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL17 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL18 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL19 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL20 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL21 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL22 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL23 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL24 / 31Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL25 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL26 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL27 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL28 / 31Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL29 / 31Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL30 / 31Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL31 / 31Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 20, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 20, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL15 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL16 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL17 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL18 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL19 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL20 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL21 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL22 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL23 / 30Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL24 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL25 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL26 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL27 / 30Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL28 / 30Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL29 / 30Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL30 / 30Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 20, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL15 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL16 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL17 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL18 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL19 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL20 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL21 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL22 / 29Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL23 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL24 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL25 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL26 / 29Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL27 / 29Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL28 / 29Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL29 / 29Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL15 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL16 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL17 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL18 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL19 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL20 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL21 / 28Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL22 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL23 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL24 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL25 / 28Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL26 / 28Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL27 / 28Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL28 / 28Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL15 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL16 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL17 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL18 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL19 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL20 / 27Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL21 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL22 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL23 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL24 / 27Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL25 / 27Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL26 / 27Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL27 / 27Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL15 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL16 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL17 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL18 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL19 / 26Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL20 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL21 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL22 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL23 / 26Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL24 / 26Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL25 / 26Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL26 / 26Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 12, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL15 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL16 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL17 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL18 / 25Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL19 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL20 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL21 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL22 / 25Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL23 / 25Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL24 / 25Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL25 / 25Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL15 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL16 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL17 / 24Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL18 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL19 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL20 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL21 / 24Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL22 / 24Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL23 / 24Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL24 / 24Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL15 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL16 / 23Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL17 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL18 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL19 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL20 / 23Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL21 / 23Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL22 / 23Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL23 / 23Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL14 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL15 / 22Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL16 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL17 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL18 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL19 / 22Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL20 / 22Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL21 / 22Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL22 / 22Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL13 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 21Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL15 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL16 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL17 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL18 / 21Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL19 / 21Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL20 / 21Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL21 / 21Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL12 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 20Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL14 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL15 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL16 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL17 / 20Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL18 / 20Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL19 / 20Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL20 / 20Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 11, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL11 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 19Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL13 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL15 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL16 / 19Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL17 / 19Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL18 / 19Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL19 / 19Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL10 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 18Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL12 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL14 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL15 / 18Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL16 / 18Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL17 / 18Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL18 / 18Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 17Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 17Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 17Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 17Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 17Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 17Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 17Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 17Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL9 / 17Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 17Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL11 / 17Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 17Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL13 / 17Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 17Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL15 / 17Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL16 / 17Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL17 / 17Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 16Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 16Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 16Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 16Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 16Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 16Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 16Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL8 / 16Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 16Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL10 / 16Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 16Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL12 / 16Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 16Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL14 / 16Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL15 / 16Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL16 / 16Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 15Show Caption +Hide Caption –
Contractors complete work Dec. 5, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 15Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 15Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 15Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 15Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 15Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL7 / 15Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 15Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL9 / 15Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 15Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL11 / 15Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 15Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL13 / 15Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 15Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL15 / 15Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 14Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 14Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 14Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 14Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 14Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL6 / 14Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 14Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL8 / 14Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 14Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL10 / 14Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 14Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL12 / 14Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 14Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL14 / 14Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 13Show Caption +Hide Caption –
Contractors complete work Dec. 4, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 13Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 13Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 13Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL5 / 13Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 13Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL7 / 13Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 13Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL9 / 13Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 13Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL11 / 13Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 13Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL13 / 13Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 12Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 12Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 12Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL4 / 12Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 12Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL6 / 12Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 12Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL8 / 12Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 12Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL10 / 12Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 12Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL12 / 12Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 11Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 11Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL3 / 11Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 11Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL5 / 11Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 11Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL7 / 11Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 11Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL9 / 11Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 11Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL11 / 11Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 10Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL2 / 10Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 10Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL4 / 10Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 10Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL6 / 10Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 10Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL8 / 10Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 10Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL10 / 10Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 9Show Caption +Hide Caption –
Contractors complete work Dec. 3, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 9Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL3 / 9Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 9Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL5 / 9Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 9Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL7 / 9Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 9Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL9 / 9Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 8Show Caption +Hide Caption – (Photo Credit: U.S. Army)VIEW ORIGINAL2 / 8Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 8Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL4 / 8Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 8Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL6 / 8Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 8Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL8 / 8Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 7Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 7Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL3 / 7Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 7Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL5 / 7Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 7Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL7 / 7Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 6Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL2 / 6Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 6Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL4 / 6Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 6Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL6 / 6Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 5Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 5Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL3 / 5Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 5Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL5 / 5Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 4Show Caption +Hide Caption –
Contractors complete work Dec. 2, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army)VIEW ORIGINAL2 / 4Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 4Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL4 / 4Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 3Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 3Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL3 / 3Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
1 / 2Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL2 / 2Show Caption +Hide Caption –
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
Contractors complete work Nov. 25, 2025, for the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project at Fort McCoy, Wis. The project description states the plan is to build the two buildings based on the standard layout depicted in the Operational Readiness Training Complex. The project calls for the construction of two new 48,000-square-foot, four-story Collective Training Officers Quarters buildings. The contract duration is scheduled for completion in 1,260 calendar days. (U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)
(Photo Credit: U.S. Army Photo by Scott T. Sturkol/Fort McCoy Public Affairs Office)VIEW ORIGINAL
Social Sharing