Last updated April 30, 2025
ANSBACH, Germany — Garrison public works crews must shut power off across USAG Ansbach installations between April to July 2025 to conduct annual maintenance on transformer stations.
These scheduled power outages will affect buildings across installations to include housing, barracks and garrison offices.
Host nation law requires yearly maintenance and inspection of transformer stations on the installations.
Expect power to be shut off on the the affected stations for approximately four to eight hours. Memos will be posted on entrances of affected buildings.
BARTON BARRACKS:
- April 26: Bldg. 5259, 5284, 5263, 5264, 5260, 5261, 5253, 5250 (Fitness Center), 5251, 5254, 5255, 5256, 5257, 5292, ACP 5298/5316, 5308
KATTERBACH & BISMARCK KASERNES:
- May 13: Bldg. 9027, 5843A, 5843B, 5843C, 5843D, 5843E, 5844, 5845, 5846, 5847, 5848, 5982, 5983, 5903, 9030, 5864, 5865, 9002, 5511, 5849, 5900
- May 23: Bldg. 5912, 5913, 5914, 5915, 5916, 5917, 5918, 5919, 5930, 5931, 5932, 5933, 5933, 5934, 5935, 5936, 5937, 5938, 5839, 9028, 5984, 9010, 5911, 5910, 5925
- June 27: Bldg. 5823, 5824 (Community Bank), 5835 (AAFES Express), 5836, 5825, 5822, 5817, 5836, 5837, 5838, 5839, 5840, 5841, 5842, 9026, 9003
- July 8: Bldg. 5940, 5941, 5942, 5943, 5947, 5920, 5924, 5944, 5945, 5946, 5948, 5949, 5950, 5952, 5953, 5954, 5955, 5507, 9022
- July 9: Bldg. 5813A, 5813B, 5813C, 5813D, 5814 (DFAC), 5988, 5806 (Hangar 2), 5807 (Hangar 1), 5815, 9033, 5818, 5819
- July 10: Bldg. 5958
- July 15: Bldg. 5809, 5888, 5891, 5513, 5850, 5810, 5805, 9007
URLAS KASERNE / SHIPTON BARRACKS:
- April 15: Bldg. 8152 (Army Lodge; Bldgs. 8400–8475 (Housing Houses)
- April 17: Bldg. 8150 and Bldg. 8156 (Clinic)
- April 22: 8001, 8002, 8003, 8004, 8005, 8007, 8012, 8014, 8033, 8009, 8033, 8013 8015, 8016, 8017, 8018, 8111, 8107, 8108, 8109, 8110, 8130, 8131, 8132, 8133, 8119,
- April 29: Bldg. 8134 (Main Exchange)
OBERDACHSTETTEN:
- May 20: Frankenkaserne
- June 17: Frankenkaserne
STORCK BARRACKS:
- May 22: Bldg. 6502, 6503, 6546, 6625, 6532 (Bank), 6651, 6544, 6513, 6514, 6516, 6517, 6518, 6528, 6544, 6591, 6530
- June 3: Bldg. 6508, 6509, 6644, 6545, 6640, 6500, 6506, 6601 6505, 6502
- June 5: June 5: Bldg. 6633, 6634, 6689, 6628, 6629, 6630, 6631
- June 10: Housing Area East
- June 12: Storck Housing East, Storck Housing West, Bldg. 6592, 6593, 6594, 6603, 6686, Sporting Field, 6541, 6504 (Fitness Center)
- June 24: Bldg. 6500, 6545, 6646, 6640, 6500, 6545, 6646, 6640
- June 28: All Storck Barracks
If you are uncertain whether a service will be closed or open, call ahead. The USAG Ansbach phonebook is available at https://home.army.mil/ansbach/contact/garrison-phonebook
Find office/organization information in the USAG Ansbach drop-down of the My Army Post app. More on the app at www.army.mil/a/282396.
Editor's note: These dates are subject to change. The USAG Ansbach Public Affairs Office will continually update this article as changes occur.