1 / 11Show Caption +Hide Caption –
Construction on a new $7.03 million shipping, receiving, and mail freight facility is shown Oct. 4, 2021, at Fort McCoy, Wis. The construction for the facility included the requirement of a pre-engineered metal building that has an estimated 19,500 square feet of space. Projects like this align with Fort McCoy’s long-range strategic planning objectives, including to sustain and modernize Fort McCoy’s cantonment, range complex, strategic mobility, physical security, quality of life, and information technology infrastructure. This project is managed by the U.S. Army Corps of Engineers. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL2 / 11Show Caption +Hide Caption –
Construction on a new $7.03 million shipping, receiving, and mail freight facility is shown Oct. 4, 2021, at Fort McCoy, Wis. The construction for the facility included the requirement of a pre-engineered metal building that has an estimated 19,500 square feet of space. Projects like this align with Fort McCoy’s long-range strategic planning objectives, including to sustain and modernize Fort McCoy’s cantonment, range complex, strategic mobility, physical security, quality of life, and information technology infrastructure. This project is managed by the U.S. Army Corps of Engineers. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL3 / 11Show Caption +Hide Caption –
Construction on a new $7.03 million shipping, receiving, and mail freight facility is shown Oct. 4, 2021, at Fort McCoy, Wis. The construction for the facility included the requirement of a pre-engineered metal building that has an estimated 19,500 square feet of space. Projects like this align with Fort McCoy’s long-range strategic planning objectives, including to sustain and modernize Fort McCoy’s cantonment, range complex, strategic mobility, physical security, quality of life, and information technology infrastructure. This project is managed by the U.S. Army Corps of Engineers. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL4 / 11Show Caption +Hide Caption –
Construction on a new $7.03 million shipping, receiving, and mail freight facility is shown Oct. 4, 2021, at Fort McCoy, Wis. The construction for the facility included the requirement of a pre-engineered metal building that has an estimated 19,500 square feet of space. Projects like this align with Fort McCoy’s long-range strategic planning objectives, including to sustain and modernize Fort McCoy’s cantonment, range complex, strategic mobility, physical security, quality of life, and information technology infrastructure. This project is managed by the U.S. Army Corps of Engineers. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL5 / 11Show Caption +Hide Caption –
Construction on a new $7.03 million shipping, receiving, and mail freight facility is shown Oct. 18, 2021, at Fort McCoy, Wis. The construction for the facility included the requirement of a pre-engineered metal building that has an estimated 19,500 square feet of space. Projects like this align with Fort McCoy’s long-range strategic planning objectives, including to sustain and modernize Fort McCoy’s cantonment, range complex, strategic mobility, physical security, quality of life, and information technology infrastructure. This project is managed by the U.S. Army Corps of Engineers. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL6 / 11Show Caption +Hide Caption –
Construction on a new $7.03 million shipping, receiving, and mail freight facility is shown Oct. 18, 2021, at Fort McCoy, Wis. The construction for the facility included the requirement of a pre-engineered metal building that has an estimated 19,500 square feet of space. Projects like this align with Fort McCoy’s long-range strategic planning objectives, including to sustain and modernize Fort McCoy’s cantonment, range complex, strategic mobility, physical security, quality of life, and information technology infrastructure. This project is managed by the U.S. Army Corps of Engineers. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL7 / 11Show Caption +Hide Caption –
Construction on a new $7.03 million shipping, receiving, and mail freight facility is shown Oct. 18, 2021, at Fort McCoy, Wis. The construction for the facility included the requirement of a pre-engineered metal building that has an estimated 19,500 square feet of space. Projects like this align with Fort McCoy’s long-range strategic planning objectives, including to sustain and modernize Fort McCoy’s cantonment, range complex, strategic mobility, physical security, quality of life, and information technology infrastructure. This project is managed by the U.S. Army Corps of Engineers. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL8 / 11Show Caption +Hide Caption –
Construction on a new $7.03 million shipping, receiving, and mail freight facility is shown Oct. 18, 2021, at Fort McCoy, Wis. The construction for the facility included the requirement of a pre-engineered metal building that has an estimated 19,500 square feet of space. Projects like this align with Fort McCoy’s long-range strategic planning objectives, including to sustain and modernize Fort McCoy’s cantonment, range complex, strategic mobility, physical security, quality of life, and information technology infrastructure. This project is managed by the U.S. Army Corps of Engineers. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL9 / 11Show Caption +Hide Caption –
Construction on a new $7.03 million shipping, receiving, and mail freight facility is shown Oct. 18, 2021, at Fort McCoy, Wis. The construction for the facility included the requirement of a pre-engineered metal building that has an estimated 19,500 square feet of space. Projects like this align with Fort McCoy’s long-range strategic planning objectives, including to sustain and modernize Fort McCoy’s cantonment, range complex, strategic mobility, physical security, quality of life, and information technology infrastructure. This project is managed by the U.S. Army Corps of Engineers. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL10 / 11Show Caption +Hide Caption –
Construction on a new $7.03 million shipping, receiving, and mail freight facility is shown Oct. 18, 2021, at Fort McCoy, Wis. The construction for the facility included the requirement of a pre-engineered metal building that has an estimated 19,500 square feet of space. Projects like this align with Fort McCoy’s long-range strategic planning objectives, including to sustain and modernize Fort McCoy’s cantonment, range complex, strategic mobility, physical security, quality of life, and information technology infrastructure. This project is managed by the U.S. Army Corps of Engineers. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL11 / 11Show Caption +Hide Caption –
Construction on a new $7.03 million shipping, receiving, and mail freight facility is shown Oct. 18, 2021, at Fort McCoy, Wis. The construction for the facility included the requirement of a pre-engineered metal building that has an estimated 19,500 square feet of space. Projects like this align with Fort McCoy’s long-range strategic planning objectives, including to sustain and modernize Fort McCoy’s cantonment, range complex, strategic mobility, physical security, quality of life, and information technology infrastructure. This project is managed by the U.S. Army Corps of Engineers. (U.S. Army Photo by Scott T. Sturkol, Public Affairs Office, Fort McCoy, Wis.)
(Photo Credit: Scott Sturkol)VIEW ORIGINAL
Work continues on a new $7.03 million shipping and receiving facility near the new Gate 20 at Fort McCoy, Wis.
Contractor Relyant Global LLC, headquartered in Maryville, Tenn., was awarded a contract of $7,030,235 to design and build the facility, said Ken Green with the U.S. Army Corps of Engineers Resident Office at Fort McCoy.
The contract called for the construction of a pre-engineered metal building that will have an estimated 19,500 square feet of space, Green said. This ongoing work includes completing all necessary infrastructure and related building needs.
As of Oct. 8, the project was approximately 99 percent complete and roof work was continuing, Green said.
Relyant Global LLC was also the contractor for another project at Fort McCoy to build seven new military family housing units in the South Post Housing area from 2019-2020.
Projects like this align with Fort McCoy’s long-range strategic planning objectives, including to “sustain and modernize Fort McCoy’s cantonment, range complex, strategic mobility, physical security, quality of life, and information technology infrastructure.”
Throughout the past decade, Fort McCoy has experienced unprecedented facility modernization, according to the 2021 Fort McCoy Executive Summary, which is produced by the Fort McCoy Garrison. The improvement effort also has included training-area development and expansion, increased training and customer-support capacity, and improved quality-of-life opportunities.
Located in the heart of the upper Midwest, Fort McCoy is the only U.S. Army installation in Wisconsin.
The installation has provided support and facilities for the field and classroom training of more than 100,000 military personnel from all services each year since 1984.
Learn more about Fort McCoy online at https://home.army.mil/mccoy, on Facebook by searching “ftmccoy,” and on Twitter by searching “usagmccoy.”
Social Sharing