


Work at the Lorain Outer Wall Repair includes but is not limited to supplying all plant, labor, equipment, and materials necessary to repair the structure and construct a standalone rectangular cell, approximately 51 feet long by 31 feet wide, within the existing breakwater's gap. The standalone cell will be constructed from four steel sheet pile walls anchored to each other with steel tie rods and wales. Additional armor stone protection will be installed below water adjacent to the new cell. Repairs to the existing cells will include installation of large cover plates over existing cracked piles located on the lake side of 12 of the breakwater's circular cells. Cover plates will be installed above and below water using structural blind fasteners and rubber spacers. Approximately 40 small solar power light fixtures are to be installed on the existing cells. (Photo Credit: U.S. Army) VIEW ORIGINAL

Work at the Lorain Outer Wall Repair includes but is not limited to supplying all plant, labor, equipment, and materials necessary to repair the structure and construct a standalone rectangular cell, approximately 51 feet long by 31 feet wide, within the existing breakwater's gap. The standalone cell will be constructed from four steel sheet pile walls anchored to each other with steel tie rods and wales. Additional armor stone protection will be installed below water adjacent to the new cell. Repairs to the existing cells will include installation of large cover plates over existing cracked piles located on the lake side of 12 of the breakwater's circular cells. Cover plates will be installed above and below water using structural blind fasteners and rubber spacers. Approximately 40 small solar power light fixtures are to be installed on the existing cells. (Photo Credit: U.S. Army) VIEW ORIGINAL


The U.S. Army Corps of Engineers Buffalo District design team designed the panels and Great Lakes Dock and Materials, LLC fabricated them. (Photo Credit: U.S. Army) VIEW ORIGINAL


Work at the Lorain Outer Wall Repair includes but is not limited to supplying all plant, labor, equipment, and materials necessary to repair the structure and construct a standalone rectangular cell, approximately 51 feet long by 31 feet wide, within the existing breakwater's gap. The standalone cell will be constructed from four steel sheet pile walls anchored to each other with steel tie rods and wales. Additional armor stone protection will be installed below water adjacent to the new cell. Repairs to the existing cells will include installation of large cover plates over existing cracked piles located on the lake side of 12 of the breakwater's circular cells. Cover plates will be installed above and below water using structural blind fasteners and rubber spacers. Approximately 40 small solar power light fixtures are to be installed on the existing cells. (Photo Credit: U.S. Army) VIEW ORIGINAL


Work at the Lorain Outer Wall Repair includes but is not limited to supplying all plant, labor, equipment, and materials necessary to repair the structure and construct a standalone rectangular cell, approximately 51 feet long by 31 feet wide, within the existing breakwater's gap. The standalone cell will be constructed from four steel sheet pile walls anchored to each other with steel tie rods and wales. Additional armor stone protection will be installed below water adjacent to the new cell. Repairs to the existing cells will include installation of large cover plates over existing cracked piles located on the lake side of 12 of the breakwater's circular cells. Cover plates will be installed above and below water using structural blind fasteners and rubber spacers. Approximately 40 small solar power light fixtures are to be installed on the existing cells. (Photo Credit: U.S. Army) VIEW ORIGINAL

Work at the Lorain Outer Wall Repair includes but is not limited to supplying all plant, labor, equipment, and materials necessary to repair the structure and construct a standalone rectangular cell, approximately 51 feet long by 31 feet wide, within the existing breakwater's gap. The standalone cell will be constructed from four steel sheet pile walls anchored to each other with steel tie rods and wales. Additional armor stone protection will be installed below water adjacent to the new cell. Repairs to the existing cells will include installation of large cover plates over existing cracked piles located on the lake side of 12 of the breakwater's circular cells. Cover plates will be installed above and below water using structural blind fasteners and rubber spacers. Approximately 40 small solar power light fixtures are to be installed on the existing cells. (Photo Credit: U.S. Army) VIEW ORIGINAL
BUFFALO, NY– The U.S. Army Corps of Engineers, Buffalo District completed repairs to the Lorain breakwater located in Lake Erie in the Port of Lorain, Lorain County, Ohio, on August 5, 2020.
Approximately 50 linear feet of the breakwater was repaired, which was void with a stone base and vertical sheet pile on top. Additionally, any of the remaining cracks were also repaired and solar powered lights were added across both sides of the entire breakwater. A cell of the Lorain breakwater was removed in 2017 due to falling in disrepair.
"A breakwater is the first line of defense against the turbulent tides of Lake Erie for many of our lake front communities. As we face the reality of rising lake levels, diligence is required to ensure the safety and navigability of many harbors in the Great Lakes region,” Rep. Marcy Kaptur (OH 9th District) said at the start of construction in May. “I appreciate the Army Corps of Engineers' partnership and attention to this important investment for the City of Lorain and its commercial and recreational harbor users and look forward to future efforts that have a direct, substantive effect on our lake front communities."
Great Lakes Dock and Materials, LLC completed the $2.1 million contract. Breakwater repairs began in May.
“The Army Corps is continually looking for ways to work collaboratively with stakeholders on all of Lake Erie’s harbors,” said Russ Brandenburg, USACE Buffalo District senior project manager. “The Lorain Harbor repair is a perfect example of how our strong collaboration with the Port of Lorain has resulted in positive benefits through infrastructure improvements for Lake Erie and the public that use it.”
Social Sharing