Fort Irwin is moving ahead from summer storm disasters

By Leslie OzawaDecember 26, 2013

Repairs continue on Fort Irwin flood-damaged builidings
1 / 2 Show Caption + Hide Caption – J&K Drywall construction workers remove damaged dry wall panels as part of general contractor Betance's work to repair electrical, wall and floor damage to Building 273. The building's basement was flooded, requiring repairs to the mechanical room's ... (Photo Credit: U.S. Army) VIEW ORIGINAL
Fort Irwin officials assess floood damage with Congressman Cook
2 / 2 Show Caption + Hide Caption – Fort Irwin director of public works Muhammad Bari (center) explains damage caused by the Aug. 25, 2013, flooding of Fort Irwin, Calif., during a tour on Nov. 6, 2013. (From left) Fort Irwin garrison commander Col. Jon Braga, Congressman Paul Cook, M... (Photo Credit: U.S. Army) VIEW ORIGINAL

FORT IRWIN, Calif. (Dec. 26, 2013) -- While Fort Irwin has resumed normal operations, efforts are continuing to repair damage caused by last summer's powerful, localized storms that resulted in millions of dollars of damage over five weeks in July and August.

Three major power outages, July 22, Aug. 18, and Aug. 29, were all caused by downed power lines in the high desert wash areas close to I-15 interstate highway, said Muhammad Bari, director of Fort Irwin's public works department. The last outage on Aug. 28, came four days after a short but powerful afternoon thunderstorm flooded numerous Fort Irwin buildings and streets, Aug. 25.

In the days following the flood, all commands on Fort Irwin, its Soldiers, family members and civilians, pitched in to restore and resume normal operations. While the Fort Irwin community is now focused more on year-end holiday festivities, work continues on more permanent repairs, as well as on fixes to the post's vulnerability to power outages and storm damage.

"During this storm, over 160 buildings got minor to severe damage," Bari noted. "Repair contracts have been let for over 95 facilities that were flooded. We had leaking roofs, flooded basements and mechanical rooms, carpet damage, wall damage."

Some of the more than $40 million worth of contracts, managed by the Army Corps of Engineers Los Angeles District, will be used to repair the most seriously damaged facilities that include two barracks, the National Training Center Operations Leader Training Program facility, and 11th Armored Cavalry Regiment squadron headquarters. Other contractors began work in December to resurface the eroded Outer Loop Road and Westbrook Road leading out to Bicycle Lake.

"The repair work requires a lot of planning and coordination," said Fort Irwin Department of Public Works engineering division's Gary Cooper. Building tenants have to be temporarily moved to other office spaces so they can continue working, before contractors can move in to do repairs.

Fort Irwin is also now working with higher Army headquarters to obtain additional tens of millions of dollars to do more work, including fortifying foundations of two bridge buildings weakened by the flood, and to update Fort Irwin's storm water management system that dates back to the 1970's.

"Fort Irwin is at the end of 30-mile long extension cord," Bari said, in commenting about the post's dependence on power lines and electricity supplied and maintained by Southern California Edison.

Bari said Southern California Edison is now conducting detailed survey and studies to evaluate electric utility infrastructure that Southern California Edison owns and operates. The survey report that will lead to upgrading the power distribution system to Fort Irwin will be submitted to Southern California Edison Corporate and Fort Irwin, by next summer.

"Short-term, [Southern California Edison] are stocking more resources. That will improve the response time to Fort Irwin," Bari said. He said that the Aug. 28 power outage required Southern California Edison to replace a downed 96-foot tall power pole.

It took several hours to bring this pole to the site as it was not a stock item, and was not readily available. The power outage duration may have been reduced if this pole was available in the stock.

Fort Irwin is working with Installation Management Command headquarters to obtain approval for permanent backup generators to be located near the child care center and other facilities that serve the community.

Long term, Fort Irwin has four renewable energy projects that are planned to be online in the next three years, said Bari.

• The Army is in the process of selecting a contractor to provide the post with power from a 15-megawatt solar panel facility to be constructed just outside the main gate to Fort Irwin.

• The $165 million hospital now being built to replace the current Weed Army Community Hospital includes a two-megawatt solar energy system that will support 90 percent of the hospital's energy needs, including heated water.

• A one-megawatt trash-to-energy facility will be built during 2013-14, on Fort Irwin. This project will help manage solid waste/trash and also provide one megawatts of electricity. The project also includes installing solar panels on carports at the National Training Center and Operations Group headquarters that will provide 750 kilowatts energy.

• A separate one-megawatt facility will be built on Fort Irwin in 2014, as a solar energy demonstration project funded by the Department of Defense Environmental Security Technology Certification Program.

Currently, Fort Irwin and the National Training Center consumes about 28 megawatts of electricity daily.

"These projects will help Fort Irwin shave its peak load that will reduce our electricity bill. We still are quite a way from being self sufficient, but these efforts are paving a way to become Net Zero energy installation in near future," Bari said.

Related Links:

Army.mil: North America News

Fort Irwin on Facebook