Stand-to! update Beginning May 2022, STAND-TO! will no longer be published on Army.mil and/or distributed to its subscribers. Please continue to learn about the U.S. Army on www.army.mil and follow @USArmy on our social media platforms. Thank you for your continued interest in learning about the U.S. Army.

Army Office of Energy Initiatives

Tuesday, October 14, 2014

What is it?

The Secretary of the Army John McHugh signed a directive to establish the Office of Energy Initiatives (OEI) as of Oct. 1, 2014. The OEI will continue the ambitious efforts of the Energy Initiatives Task Force (EITF) which was established in September 2011. The OEI will serve as the Army’s central management office for the development, implementation and oversight of all third-party financed, large-scale (greater than 10 megawatts) renewable and alternative energy projects.

The OEI uses a balanced enterprise approach guided by three driving principles: Energy security through access to resilient, sustainable renewable energy sufficient for critical mission operations; economic benefits and predictability as projects are cost neutral or provide cost avoidance at day one of operations; and all projects contribute to meeting mandates established by executive orders and national defense authorization acts.

What has the Army done?

The OEI has screened nearly 200 Army, Reserve, and National Guard installations to determine the best potential for large-scale renewable energy development. Working with Defense Logistics Agency – Energy, the Army Corps of Engineers, along with using pre-existing General Services Administration Areawide contracts, the OEI has a dozen projects representing more than 350 Megawatts (MW) either under construction or in the contracts and agreements phase.

  • –Fort Huachuca, Arizona - approximately 18 MW Solar
  • –Fort Drum, New York - 28 MW Biomass
  • –Fort Detrick, Maryland - approximately 15 MW Solar
  • –For Irwin, California - approximately 15 MW Solar
  • –Fort Stewart, Georgia - 30 MW Solar
  • –Fort Benning, Georgia - 30 MW Solar
  • –Fort Gordon, Georgia - 30 MW Solar
  • –Redstone Arsenal, Alabama - up to 18000 MW per year Solar
  • –Schofield Barracks, Hawaii - 50 MW Biofuel
  • –Fort Hood, Texas - up to 40 MW Solar/Wind
  • –Redstone Arsenal, Alabama - 25 MW Combined Heat and Power (CHP) Steam and Electricity
  • –Tooele Depot, Utah - Wind/ Solar

In addition there are another dozen projects totally approximately 200 MW of additional renewable energy which are in earlier phases of development.

What does the Army have planned for the future?

The Army continues to push forward to achieve mandated renewable energy goals, refine project management and execution processes, and achieve the OEI mission to Secure Army Installations with Energy that is Clean, Reliable and Affordable. The OEI team provides broad experience and capabilities in acquisition, project finance, renewable technologies, real estate, utility regulation, grid integration and environmental permitting, assisting installation commanders and their staffs to assess and implement renewable energy projects.

Why is this important to the Army?

Installation energy security remains a top priority for the Army and is reflected in the Secretary of the Army’s Top 10 Priorities – Develop effective energy solutions.