2 Afghan National Police projects in Daykundi province underway

By Karla Marshall, USACESeptember 19, 2011

2 Afghan National Police projects in Daykundi province underway
1 / 2 Show Caption + Hide Caption – Workers at the Miramor district police headquarters project site prepare concrete for the perimeter wall foundation Sept. 11, 2011. The U.S. Army Corps of Engineers is building this headquarters complex to enable the Afghan National Police to provide... (Photo Credit: U.S. Army) VIEW ORIGINAL
2 Afghan National Police projects in Daykundi province underway
2 / 2 Show Caption + Hide Caption – Hans Miller, project engineer at the U.S. Army Corps of Engineers Afghanistan Engineer District-South, Tarin Kowt Resident Office, discusses the construction of the perimeter wall at the Afghan National Police project site in Gaiti, Daykundi province... (Photo Credit: U.S. Army) VIEW ORIGINAL

DAYKUNDI PROVINCE, Afghanistan, Sept. 17, 2011 -- Last summer and fall, the U.S. Army Corps of Engineers awarded contracts for $1.8 million and $1.5 million to construct two Afghan National Police district headquarters compounds in the Gaiti and Miramor districts. The compounds will enable the Afghan National Police to provide security in these remote mountain areas. These projects were funded by the Combined Security Transition Command-Afghanistan.

"Afghans need to know that their government is able to provide essential services, including security," said Lt. Col. John Carpenter, intelligence chief at the Afghanistan Engineer District-South. "By constructing these types of compounds, the U.S. moves the government of Afghanistan a step closer to that goal."

Consisting of perimeter walls, guard towers, office space, a dining facility, barracks, vehicle parking and storage facilities, the compounds each will accommodate 60 personnel and are scheduled to be complete in late 2012.

"There are a few significant impediments that delay construction in Daykundi province," said Hans Miller, project engineer on both the Gaiti and Miramor projects who deployed from USACE's Fort Worth District. "For instance, Wahid, our USACE quality assurance representative, said it takes more than 60 hours to drive from Kabul to Gaiti, a distance of less than 185 miles, because the roads are narrow, unpaved and wind through the mountains."

Other challenges include site preparation, the lack of skilled workers and weather extremes.

"At Gaiti and Miramor, our contractors are excavating through granite with relatively unsophisticated machinery to pour foundations for the perimeter walls," said Miller. "They recruit workers from the local area who have very little construction knowledge so training has to be a part of the process. Also, the contractors cannot work from mid-October through February because snow makes the mountain roads impassable."

Although delays are built into the construction schedule, project engineers and managers push contractors to keep construction on track.

"We can't get to these remote locations as often as we would like," said Miller, adding, "so we rely on our quality assurance representatives to keep us informed of progress. If we know the problems, we can help contractors find solutions. QA representatives, like Wahid, are critical to our efforts because they help USACE create the conditions for a secure Afghanistan."