• Progress continues on the Biotreatment Electrical Building. The Biotreatment Electrical Building and the caustic tank are located in the Biotreatment Area.

    Biotreatment Electrical Building

    Progress continues on the Biotreatment Electrical Building. The Biotreatment Electrical Building and the caustic tank are located in the Biotreatment Area.

  • Rebar and formwork is installed to frame the doors of the Munitions Service Magazines.

    Munitions Service Magazines

    Rebar and formwork is installed to frame the doors of the Munitions Service Magazines.

  • Subcontractors have been installing duct work, which now tops the Automated Guided Vehicle Corridor and the Agent Filtration Area.

    Automated Guided Vehicle Corridor

    Subcontractors have been installing duct work, which now tops the Automated Guided Vehicle Corridor and the Agent Filtration Area.

  • Cable tray, process piping and interior composite walls now enclose the agent hydrolyzer tanks inside the Agent Processing Building.

    Agent Processing Building

    Cable tray, process piping and interior composite walls now enclose the agent hydrolyzer tanks inside the Agent Processing Building.

  • Structural steel fire proofing is currently taking place inside the Enhanced Reconfiguration Building near the Explosion Containment Rooms (right).

    Enhanced Reconfiguration Building

    Structural steel fire proofing is currently taking place inside the Enhanced Reconfiguration Building near the Explosion Containment Rooms (right).