• The agent water separator tanks (right) and the Munitions Wash Station wash water collection tanks are now in place in the Agent Processing Building.

    Agent Processing Building

    The agent water separator tanks (right) and the Munitions Wash Station wash water collection tanks are now in place in the Agent Processing Building.

  • Workers install rebar for three explosive containment rooms.  Explosive components will be removed here.

    Enhanced Reconfiguration Building

    Workers install rebar for three explosive containment rooms. Explosive components will be removed here.

  • Members of the Colorado Chemical Demilitarization Citizen’s Advisory Commission toured the PCAPP site in April. John Thatcher (red jacket) and Irene Kornelly ask questions of Gary Anderson, PCAPP site project manager (right), and Mark Hunter, Bechtel lead field civil engineer (far left).

    Construction Site Tours

    Members of the Colorado Chemical Demilitarization Citizen’s Advisory Commission toured the PCAPP site in April. John Thatcher (red jacket) and Irene Kornelly ask questions of Gary Anderson, PCAPP site project manager (right), and Mark Hunter, Bechtel...